V_V2 CHanged the COnfirmed Quantity to 0

Former Member
0 Kudos

Hi SD Gurus,

We have a background job that runs V_V2 nightly. This morning, I checked one sales order that was changed. The Confirmed quantity was changed from 5000 to 0. I am not sure why this happened because there is stock for that material in MMBE. Am i missing anything here?

Thanks,

Jograd

Accepted Solutions (0)

Answers (1)

Answers (1)

sachin_bhonsle
Explorer
0 Kudos

Hi,

Rescheduling run will only snatch away confirmed quantity from a Sales Order if there is another Sales Order/ STO with higher "priority" seeking stock for delivery.

Rescheduling "priority" can be set by sequencing parameters like Document Category, Delivery Priority, Creation date, Document Number, Item Number as per the business logic you want.

I would suggest to first have a look at MD04 for the material in question and check the stock allocation.

You can find out which documents have snatched the confirmation from the order in question.

You should be able tp pin point the issue, using this.

Else please let me know your observation, in case you require further help.

Thanks

Sachin