on 02-24-2009 4:00 PM
Hi people,
I trying to execute the prepare phase with the upgrade assistant and i get the next message error:
ERROR: To be able to use ASU Toolbox, your system requires
the ST-PI software component with at least Support Package Level 8
After the update is done, the module must be repeated!
For more information, see the upgrade documentation
It´s necessary to have the add on st-pi installed in your R3 for the upgrade to ECC 6.0???
More thanks
Hello,
download the latest SAPup from the marketplace, delete the content of the upgrade directory, start PREPRARE from the CD and extract the actual SAPup to <upgrade directory>/bin.
This helped in my case. The message still appeares, but you can go on. In a later phase you must decide for the Upgrade of ST-PI.
Greetings
Christian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Seems like you need ST-PI patch 8 and is ponting to the documentation... so it should be a prerequisite... Anyhow patching ST-PI is not a big problem... just download the patch(s) required and apply via SPAM.
If I was you I'll go through the pre-upgrade steps again.
Regards
Juan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
76 | |
9 | |
8 | |
7 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.