Hi Gurus,

We have maintained 01 inspection type for externally procured materials.At the time of each GR inspection lot gets generated.But the lot number is skipped by one number.For eg. at first GR the lot no. is 1 & for next GR the lot no. is 3. Why the system is skipping the number.

Regards

Amit

Accepted Solutions (1)

Accepted Solutions (1)

former_member186399
Active Contributor
0 Kudos

Dear Amith

Please find below posting on the same issue. Interesting issue

Link: []

Regards

gajesh

Former Member
0 Kudos

Hi Gajesh

thanks for your reply

Regards

Amit

Answers (2)

Answers (2)

Former Member
0 Kudos

Satisfied with answer

Regards

Amit

Former Member
0 Kudos

Hi Amit,

There is a number range buffer of 50 for inspection lot .

If u want to avoid skipping of the numbering

go to SNRO transaction input the object QLOSE and change the no of numbers in buffer to 1

Regards

Venugopal

0 Kudos

Hi Amit,

Venugopal is right.

Regard's

Deven

Former Member
0 Kudos

Hi Venugopal,

Thanks for your reply

Regards

Amit