cancel
Showing results for 
Search instead for 
Did you mean: 

How to link Cost plan data with budget value

Former Member
0 Kudos

Dear Experts,

I want a scenario like, my budget for a particular wbs should be same as my plan value.

How to address this in sap.

Any development required or standard sap assit this.

Regards

Ashis

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Ashis,

If i understand your requirement correctly , you need to have the budget values same as your plan values.

For this i would suggest that you create your plan using cj40. Then if this plan is approved. now you can use t-code IMCCP3 to copy your plan to budget. After this your plan values = budget value.

hope this helps you.

regards

Sandeep

Former Member
0 Kudos

Hi Sandeep,

no i m not talking about the initial budget which is the replica of plan.

My question is system should stop us when we r changing original budget without changing the original plan just to make my plan and budget value in sync.

regards

ashis

Former Member
0 Kudos

In CJ30, select WBS elments and then from top menu select 'Edit->CopyVirew" and then "Planned Total" from the list and mention percentage 100.

Former Member
0 Kudos

Dear All,

i think i have not made u clear the question.

When i am saying plan = budget, means during the project execution if somebody wants to change the budget or transfer budget from one wbs to another wbs,

then system should not allow unless untill we made the similar changes in planning data in CJ40.

"means system should force us to work in discipline manner"

Regards

Ashis

Former Member
0 Kudos

U have to go for development. Check with ABAPer.

venkatesh_kulkarni1
Active Participant
0 Kudos

GO to CJ30

enter

Select Planned values column

then select all

Edit Copy view 100% anuual as weel as Overall values select.

enter

now check your budget values

Save

Former Member
0 Kudos

hi

enter the cost planning in CJ40

copy the planned value as Budget in CJ30.