on 02-24-2009 6:13 AM
Dear Experts,
I want a scenario like, my budget for a particular wbs should be same as my plan value.
How to address this in sap.
Any development required or standard sap assit this.
Regards
Ashis
Hi Ashis,
If i understand your requirement correctly , you need to have the budget values same as your plan values.
For this i would suggest that you create your plan using cj40. Then if this plan is approved. now you can use t-code IMCCP3 to copy your plan to budget. After this your plan values = budget value.
hope this helps you.
regards
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In CJ30, select WBS elments and then from top menu select 'Edit->CopyVirew" and then "Planned Total" from the list and mention percentage 100.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
i think i have not made u clear the question.
When i am saying plan = budget, means during the project execution if somebody wants to change the budget or transfer budget from one wbs to another wbs,
then system should not allow unless untill we made the similar changes in planning data in CJ40.
"means system should force us to work in discipline manner"
Regards
Ashis
GO to CJ30
enter
Select Planned values column
then select all
Edit Copy view 100% anuual as weel as Overall values select.
enter
now check your budget values
Save
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
enter the cost planning in CJ40
copy the planned value as Budget in CJ30.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.