on 02-24-2009 5:54 AM
Hi Experts,
I am using Invoicing plan functionality to purchase materials by using Milestones from Network of Project System. The system is allowing to post Vendor Invoice (MIRO) without removing of Billing Block of Invoicing Plan from PO and the system should give error message because of non removal of Billing block.
The following configuration was done in Invoicing Plan of PS.
1. Assigned Date Category to Invoicing Plan Type (30)
2. Assignment of Invoicing Plan Type to Network Profile
The following configuration was done in Invoicing Plan of MM.
1. Assigned default date category to Partial Invoicing Plan type
2. Maintained Date category to Invoicing Plan type
3. Assigned Date proposal category to Invoicing Plan Type
4. Maintained Date Proposal to Invoicing Plan Type
What are the changes needs to do in configuration or transaction to prevent to post vendor Invoice because of nonremoval of Billing block from Invoicing Plan?
Please give me the solution.
Thanks in advance,
Rao
Hi Rao
You need to have the invoicing plan done in Project System (PS) under the project with Milestones and save the plan. On dong this, the system would generate a 'Reference Number'. This can be seen when you again go to the invoicing plan.
Use this reference number in the MM invoicing plan to link the PS & MM plans. This would create a block automatically in MM which can be lifted only on confirmation of the appropriate Milestone in PS.
Hope this helps
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There is a fuctionality for Invoicing Plan in standard SAP. You need to copy the dates from milestones. They cannot be entered manually. If manual dates are entered, there is no billing block.
Kind regards, Aleksandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As for as I know, milestone billing can be used to raise invoice only with Customer, but not with Vendor.
In Milestone billing you are linking your sales order with the WBSE (marked as billing element), & In milestones, you are specifying the usage as "sales document date". That's how your milestones get linked to your billing plan in sales side.
I don't see such feature for Vendor payment.
Experts, if anything like that available in standard SAP, please update here. It'll be one good learning.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.