on 02-24-2009 3:38 AM
Hi ,
I am working with Extended Classsic scenario.
Problem is with PO with Multiple account assignement.
There is only one user who is getting problem with one particular account assignement "CCC" - Cost Center RP.. . When PO gets created with this particular AAC , it goes into "Error in process" only for one user.
In RZ20 it shows messsage as "Please enter quantity or percentage for account assignment" & "Distr. ind. and partial invoice ind. must be set f or multi acct. assgt.".
On other hand , other users are able to order the PO with the same AAC without any error.
What could be the reason behind this only for one user ?
Regards,
Sheetal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
I have checked it intially and both are identical.
Initialy the problem was, user had entered 128 times AA line items ( added & deleted ) in the PO while in the SC it was having only 64.... Our system accepts line items till 99 , so i asked him to delete the items above 99 ..
So after that POs error has gone and it went for approval..
But after approval it again went into error in process
Sheetal