Dear all,

could you help me on this question?

i want to keep the start and finish dates of all activities fixed whenever i do the scheduling correctly.

but the fact is these dates will change unexpectedly. some finish dates will be extended a lot.

in order to solve the problem, i plan to use project version.

when i want to save the dates of all activities, i create the project version.

but how i can compare the activities dates in the project version with the actual dates i confimed?

i want to see them in a report?

how can i do that?

could you explain it in details?

thanks a lot.

Judy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

In CN47, in DB Profile and select Version Data. Then check box "Version Data" and Project version is displayed in selection screen.

Check the Version Data check box and select Project Version..

U can compare dates from Project version with Current Project Data.