on 02-20-2009 10:18 AM
Hello,
I have several phases and tasks in a project and when I release the project only the first phase is also released. I am not working with approvals.
Is the a possible to release all phases when the project is released?
Thank you and have a nice weekend,
Vanessa
Hi Vanessa,
You can create an implementation of BADI dpr_events, with filter dpr_tv_badi_method = ON_DPO_RELEASED.
ir_sender instance will be the project in that case, so you can easily retrieve the phases object and release them at this moment.
Matthias