Release all phases and tasks if project definition is released

former_member184588
Active Participant
0 Kudos

Hello,

I have several phases and tasks in a project and when I release the project only the first phase is also released. I am not working with approvals.

Is the a possible to release all phases when the project is released?

Thank you and have a nice weekend,

Vanessa

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Vanessa,

You can create an implementation of BADI dpr_events, with filter dpr_tv_badi_method = ON_DPO_RELEASED.

ir_sender instance will be the project in that case, so you can easily retrieve the phases object and release them at this moment.

Matthias

former_member184588
Active Participant
0 Kudos

Hello Matthias,

thanks for your valueable answer. This sounds really good ..

Thanks and have a nice weekend,

Vanessa

Former Member
0 Kudos

Hello, Vanessa Martinez,

Our solution is define user status profile and develop workflow.

Our problem is sequential release tasks.

Regards,

Liu Qi Wei