on 02-20-2009 10:14 AM
Hello Experts,
I'm running report CN50N to see the assignment of personel to the internal network activity. I've assign some persons for test and there was an extra line reported with zero capacity / no personel assigned. I thought that maybe this line represents some unassigned hours, but when I left some hours, I've received three lines: personal assignment / hours not assigned and additional line without hours...
Any idea if this is standard functionality and what is the functional meaning of it?
Thank you for your help, Aleksandra
Hello
Thats a standard functionality. That in fact represents the counter no: 0 in the back end table. It might be an irritant but it does not change anything so nothing to worry about. Why it was provided is an answer maybe SAP programmers can answer. If you have an ABAPer you can ask him to remove that line in a new custom report.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.