Hi friends,

I have customer requirement that customer want that message should not display .

no budget is maintained but still this warning message is comming in the shopping cart screen in additional specification .

Can any body suggest me how to remove this message in nots for approval

Path : SRM 5.0 in Monitoring shopping cart->define search -> select any shopping cart-> additional Specification :

Budget warning message

This shopping cart may cause one or more budgets to be over

committed:-

Item Description Cost Centre Financial Year

Price % Committed Budget Total Committed

-


1 Test for Limit ch SS0406

0.00 999 0.00 0.00

End of budget warning

Thanks in advance.

Edited by: Rashi on Feb 19, 2009 10:21 AM

Edited by: Rashi on Feb 19, 2009 10:22 AM

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Thanks all.

Former Member
0 Kudos

HI,

YES, will remove this message when no budget was maintained for product.

using bbp_budget_check can completelly deactivate the budget check.

Best practise first test in quality or test system then implement in production system.

Thanks

prasad.s

Former Member
0 Kudos

pls let me know how to activate the budget check for SC

Former Member
0 Kudos

Hi ,

I am still waiting for solution....

I dont want to deactivate budget check.

Problem is related that in the message is showing incorrect value of budget. While changing shopping card its not comparring the budget value from R/3 system.

In R/3 FM is used to fetch budget information but every time its giving me same vale for diffrent GL account.

Can any body helo me on this.

Thanks

Former Member
0 Kudos

Hi Rashi,

If you dont want to check budget the implement this badi

BBP_BUDGET_CHECK-->method DETERMINE_BUDGET_CHECK

Pass the parameter value NO_BUDGET_CHECK = 'X'.

your problem will be resolved

regards

Sachin

Former Member
0 Kudos

Hi Sanjeev/ sachin

Thanks for your quick responce .

Can I remove this message when no budget is maintained for the product.

mean while i am applying your suggestion ..

Please suggest me....

Former Member
0 Kudos

Hi All,

Still waiting for solution.

Thanks

Former Member
0 Kudos

I have a question for the the BADI BBP_BUDGET_CHECK.

Does this BADI just available in SRM system!? Because I can't find it in my ECC system with SE18.

So , is there any other BADI or Enhancement for ECC to do the Budget check !?

former_member206968
Active Contributor
0 Kudos

Hi,

If you want to deactivate budget check completely, then you can use badi BBP_BUDGET_CHECK. This would completely deactivate budget check, so pl. ensure that you don't want to have any check before implementing this badi.

Regards,

Sanjeev