Hi PPl

I am currently working on Actions in Audit Management (PLMD_AUDIT). We have requirement to put some validations in the field Actual Finish Date (Field name: ACTUALFINISHDATE). Hence i would like know the user exits where i can build custom validation.

Thanks in advance

Murali

Accepted Solutions (1)

Accepted Solutions (1)

former_member186399
Active Contributor
0 Kudos

Helo

Standard BADIu2019s are there available for this.

Please check for the same in

SPRO> Cross Application Componenets > Audit Management > System Adjustments> Bussiness Ad ins> Badi for managing individual audit components> Audit linkage objects with corrective action

Also check in general Badis also

Regards

gajesh