on 02-19-2009 12:55 AM
Hi Experts,
I have configured Change Request Management(CHaRM) in Solution Manager 7.0 EHP1.
Here is a scenario, after Tester successful test and change actions to "u201CConfirm Successful Testu201D from Actions. Then Change Manager change the status to "Release for Production" from Actions. Now the status change "Authorize to Import" and IT Operator / Basis Administrator "Import Correction to Production System" from Actions. And it's working fine.
Question is, Instead of IT Operator / Basis Administrator select "Import Correction to Production System" from Actions, is there any background job can schedule which will do the same work as IT Operator / Basis Administrator perform after CHANGE MANAGER's approval.
Solution Manager found program /TMWFLOW/SCMA_QUEUE_IMPORT, /TMWFLOW/SCMA_BTCH_SYNC_TEST, /TMWFLOW/SCMA_TRORDER_IMPORT but no use.
I will appreciate help.
Thanks
RS
Hi,
Your question leads to "MASS" Change of status of your Change Documents. To be more clear, if you say "Import Correction to Production System", it performs two actions
1. The actual import into production
2. Change the action of the Change Document to "Production" and additionally it may change the status of Change Request (if there is any status to be changed).
There is no automatic way of scheduling this. It has to be done manually.
Hope this answers your question.
Feel free to revert back.
-=-Ragu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ragu,
Thanks for your swift response. After research I found that there is a program CRM_SOCM_SERVICE_REPORT can schedule on background which not only import transport request into production but also changed the status of document from "Authorize to Import" to "Production".
I have not tested yet, but I found from help.sap.com.
Thanks
RS
Hi,
The report CRM_SOCM_SERVICE_REPORT is to change the status only, this is when the message is struck in some status. You cannot be sure if this report would change status all the time.
It cannot schedule the job to import.
Check my reply in this thread.
Hope this answers your question.
Feel free to revert back.
-=-Ragu
Hi Ragu,
I am taking back my comment earlier. This morning when I tested CRM_SOCM_SERVICE_REPORT with entering Transaction Number (single or multiple does not matter) whose status was "Authorize to Import" and select radio button "Set Next Status Value" and it's really works. Even when I went to calendar, I can see under "Daily Overview" "Import Transport Request (Online)".
Thanks for all your effort and time to response this thread.
-RS
Hi Ragu,
Yes, I checked the transport is in QA and PROD.
Still I have one more question on that report CRM_SOCM_SERVICE_REPORT.
When I schedule in background, it's executing all request (transaction number), I am looking where I can put only process if the status "Authorize to Import". I will appreciate.
Thanks
RS
Hi Ragu,
Thatu2019s the problem I am struggling on that report. There is no selection option for Status. Otherwise I could easily schedule background with variant of status user status Authorize to Import, or any other status which system will recognize only those transaction number to import and change status NOT all transactions.
Please let me know, if any other way can achieve the same.
Thanks
RS
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.