on 02-18-2009 12:28 PM
Hi All
I want to use pegging functionality. In my scenario i am usin one top level project and other projects are linked with that project through subnetworks. Procurement takes place at top level WBSe and then material move from top level to the 5th level WBSe in other lower levl project.
How can i use Pegging in my scenario.
Regards
Hi...
Have a look on this link.
http://help.sap.com/saphelp_di46c2/helpdata/EN/1d/e1073e254411d2b40c006094b9c9be/content.htm
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear....Saqib,
Actually im not having sufficient knowledge on this concept.
but i have collected some information plz refer....
http://projectsystems.wordpress.com/2008/01/02/gpd-grouping-pegging-and-distribution/
http://help.sap.com/saphelp_di46c2/helpdata/EN/49/7db835295f962de10000009b38f839/content.htm
Seniors...and...Experts......plz thrash out.
Regards
Chandra