on 02-17-2009 8:50 AM
Hi Experts,
We are creating a project based in another project with planned costs on it, but the costs are not being copied.
Any idea on why can this be happening?
Thanks in advance.
Kind regards,
Neil
that is correct as per standard SAP
if the planning costs are done using cost element planning or structural planning then these are not copied from operative projects
this is why network costing is useful - as network costing is carried across
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
But we are talking about costs planned from an operative project to an operative project, not from template to template. Are we talking about the same scenario?
Sorry, but I think I've seen this working...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
if you are using cost element planning via transaction CJR2 then you can use flexible upload - from excel to SAP
I have never had this requirement and it is quite amusing - so can't tell about exits
But I do not believe that there is a exit for this
can check if BADI WORKBREAKDOWN_UPDATE can be used on save