on 02-17-2009 7:57 AM
Hi All,
I am currently using ECC6, and have noticed the following for Budget Availability check:
If budget availability check is configured to check against the overall (planned) budget, the check (and warning/ error) will kick in at WBS level. However, when it is configured against the overall released budget, it will only kick in when the overall budget AT PROJECT level has been exceeded.
Can anyone confirm this?
Thank you very much.
Thanks all for the replies.
To sum up:
1) Budget availability check is indeed at WBS element level.
2) If the setup is such that warning is given for PR and error is given for PO, an error will NOT be triggered for PR - PO conversion case, since warning was already given at PR creation stage.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For point 2: The system will issue error message if the value from PR to PO increases
example:
Case 1
Budget: 43K
Availability control setting:
- Transaction : PR, Action : Warning, Usage: 100%
- Transaction: PO, Action: Error, Usage: 100%
You create PR 43K and then create PO 43K, the system will not issue error message since the value is not increased, the availability control doesn't check the budget again
Case 2
Budget: 43K
Availability control setting:
- Transaction : PR, Action : Warning, Usage: 100%
- Transaction: PO, Action: Error, Usage: 100%
You create PR 40K and then create PO 43K, the system will issue error message because from PR to PO the value is increased 3K
From 2 cases above, even the POs have the same value (43K) but the system issues error message on case 2 only
Please check note 783161 - Availability control check only if assigned value increases for clearer explanation and examples
Edited by: Kealin F on Feb 18, 2009 5:47 AM
If you chekc your budget profile in OPS9 and take help of F4 you will get the inputs for issue.
Availability control indicatorIndicator which controls whether availability checks are conducted against the overall value or against annual ones.
Use
In the project budget profile, the "Overall" indicator, used in conjunction with the "Releases" indicator, has the following effect:
Ind. 'Overall' Ind. 'Releases' Avail. control against ...
X - Overall budget
- - Annual budget
X X Overall budget released
- X Annual budget released
X = Indicator is set, in other words, checkbox was checked.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for the reply. I am aware of the above. However it does not specify the behaviour of the availability check. With reference to the SAP Help documents:
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm|http://help.sap.com/saphelp_erp60_sp/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm]
the following is mentioned:
"Dependent on the settings in the budget profile, availability control checks against one of the following values:
Current overall budget in controlling area currency
Current overall budget in object currency
Current annual budget in controlling area currency
Current annual budget in object currency
Released overall budget in controlling area currency (only for projects)
Released overall budget in object currency (only for projects)
Released annual budget in controlling area currency (only for projects)
Released annual budget in object currency (only for projects)"
From the above, the text gives the impression that availability control checks for released budgets apply only for projects.
For my case when I control at overall budget, the check will be triggered at the lowest level WBS where budget is planned. However when I control at released overall, the check will only kick in at the level 1 WBS element (i.e. grand budget total at project level must be exceeded).
Can anyone confirm this?
Dear Daniel,
That is not correct.
If you set the availability control against released budget, the system will check against released budget in the lowest WBS element (in which you release the budget in CJ32)
I think what SAP document means by (only for projects) is that budget release function only applies for project, it doesn't apply for Internal Orders
Regards,
-K-
My availability check settings are as follows:
Activation Type = 1
Overall = <Checked>
Releases = <Checked>
My overall project budget is, say, 70k. I have released 43k budget for WBS element 1. However with availability control active, I was still able to post a PO against WBS element 1. It was only blocked when I tried to post another PO such that total cost > 70k. =(
Yes,
The overall planned budget for the project (original + supplements) is ard 70k.
Planned budget for WBS element 1 (original + supplements) is ard 43k.
The full planned budget was released using CJ32; after which I managed to raise a PO of value 45k that was assigned to WBS element 1.
Hope this clarifies.
Cheers.
User | Count |
---|---|
97 | |
10 | |
10 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.