how to handle project termination i.e. when a project doesn't follow normal closure procedure.
Thanks!
This is not ideal way , but you can think of set lock master data sys. status on it. and forbidd all type of financial posstings related business txn via user status if you have used.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
you can use User Status Profile with "TRMD - Terminated Status and restrict all the changes in the business transcation
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
this is a business process issue
in the system the project will be closed anyway i.e. status set to CLSD after necessary validation by the business
e.g
A project is started in REL condition and going on
Suddenly client decides not to go through and pays necessary compensation as per contract
immediately TECO it so that no more commitments etc can be raised and no more cost booking
then make sure that all the finanacial transactions are completed and then set CLSD
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.