Hi,

Mine forecast is not getting transfered.

Maintain the distribution setting in APO with Logical system and Plant along with PIR.

Created activity,transfer profile run the schedule job

Material and plant already in place at APO System.

Checked the log book

check the spool of the batch job it says material in plant is not planned

where as in case of other material its shown as SUCCESSFUL transfered to R/3 in the spool then also its PIR is not getting reflected in MD63

Weather the material and location has to be assigned to Active model in APO Master data?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check in APO location product (transaction /n/sapapo/mat1) has the location product valid and is assigned to active model 000.

The system is telling you that the combination of location and product is not defined in SCM system or not assigned to active model.

Former Member
0 Kudos

Yes the model is assigned to plant and material

the error now is Planning horizon is smaller than past horizon of the forecast

forecast key figure does not correspond with the planning row

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Jimmy,

Check weather there is active integration model (created and activated thr CFM1 & CFM2) is available for your Material and Plant for Plann. independent requirements exists or not.

Because unless and until there is active model system will not transfer req. to ECC.

Regards,