Dear all,

While Remote client copy i got below error, please help me in this.

LOG FIlE

================================================================

Client copy from 16.02.2009 17:20:59

System ID............................ DEV

Target client........................ 600

R/3 Release.......................... 700

Basis Support Package...............SAPKB70014

Host................................. sapwtdev

Start in background............. .....

User................................. SAP*

Parameter

Source destination......................600 to PRD 450

Source system.........................PEW

Client in source system..............450

Users in source system..............BASIS

Basis Support Package...............SAPKB70014

Copier profile:.......................SAP_ALL

Table selection

Customizing data .....................X

With application data................ X

Initialize and recreate......... X

Change documents are not copied

Test mode (without database update).. R

Start analysis of system 17:20:59

Table J_3RF_PRECMET is convertible to the RFC system, field missing locally

Table PFO_GO_00IP is convertible to the RFC system, field missing locally

Table PFO_GZO is convertible to the RFC system, field missing locally

Table PFO_SEG is convertible to the RFC system, field missing locally

Table TCACS_STMTY is convertible to the RFC system, field missing locally

5 Tables cannot be converted

There are 508 non-critical differences in the table structures

Table definition A982 missing in the target system

Table definition IDITSR_GROUP_COD missing in the target system

Table definition PFO_GO_00IS missing in the target system

Table definition PFO_GO_00IV missing in the target system

Table definition TPFO_ARCH_STAT missing in the target system

Critical differences: Missing tables: 5

=====================================================

Madhu G

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Refer to note 557132 and notes attached in this.

Hope this helps.

Manoj Chintawar

Answers (1)

Answers (1)

Former Member
0 Kudos

When you are performing Remote Client Copies you must first ensure that the 2 system are in sync with Customization (TMS - transports). All Customizing/Configuration must be in sync otherwise you'll have to fix the config one-by-one. (or do a system copy).

Rgds