cancel
Showing results for 
Search instead for 
Did you mean: 

Project claim processing

Former Member
0 Kudos

Hi

I am not able to see CO documents in status bar while processing a claim. Please advcie me what may be the problem.

1) Created a claim " C1" type

2) assigned vendor

3) Defined the costing variant

4) Assign material and have approved the claim.

5) cost has been updated

But................ unable to see the CO document

Even controlling scenerio has been defined for Notification type>

Makwana

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Cost from Claim will not booked directly on WBS. If the BADI is activated then system will create Internal Order once claim is approved. The actual cost is booked on the Internal oder by PO and transfer to WBS by settelment.

The Cost u mention in the claim is planned cost.

Answers (1)

Answers (1)

Former Member
0 Kudos

dear,

It will help you.

Sukhveer