Network Type Parameters

Former Member
0 Kudos

Hi,

if i leave the "plan cost calc." as blank in OPUV then how it will process.

Thanks!

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks! everybody

Former Member
0 Kudos

System will not calcualte the plan cost and in reports you will get planned cost as Zero.

Regards,

Nitin

virendra_pal
Active Contributor
0 Kudos

then plan cost will never be determined or updated

you will have to manually trigger cost plan calc from planning board