if i leave the "plan cost calc." as blank in OPUV then how it will process.
Thanks!
Thanks! everybody
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
System will not calcualte the plan cost and in reports you will get planned cost as Zero.
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
then plan cost will never be determined or updated
you will have to manually trigger cost plan calc from planning board