on 02-16-2009 8:12 AM
My client expects monthly production schedule based on actual scheduling and capacity. The shop in-charge should know which production order should be launched first. The load for a week with details of extra capacity requirements and out sourcing details should be available from the system.
Is this possible in PPDS with any standard reports.
pls guide.
vinay
Edited by: vinay on Feb 16, 2009 9:12 AM
In Receipt View "/SAPAPO/RRP4 - Receipts View " you can see date and time for Production orders. In Planning book for Capacity view with "weekly time bucket profile" you can check for additional capacity requirement for your individual resource (after your planning run). you can also use capacity levelling feature for capacity adjustment across horizon.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi vinay,
Your requirement can be met with the following transactions
1) /n/sapapo/rrp4
2) /n/sapapo/rrp1
3) /SAPAPO/CDPS_REPT
4) /SAPAPO/PPL1
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.