on 02-16-2009 7:09 AM
Dear All,
I having a doubt how does the system calculates the POC actual- I have taken Time Proportionate for Plan in progress Tab of activity and work for actuals.
i have only 3 activities in 4th level WBS and all are confirmed- but still it is showing 13.8 as actual POC
also all my WBS have Percentage weightage as 100.
i am not able to understand this. pl. help me out
POC act
Proj Def 0.0
Wbs lvl 1 82.0
wbs lvl2 0.0
wbs lvl2 0.0
wbs lvl2 0.0
wbs lvl2 0.0
wbs lvl2 0.0
wbs lvl2 82.0
wbs lvl 3 82.0
wbs lvl 4 13.8
Act 100.0
Act 100.0
Act 100.0
done thnks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The percentage of completion describes the ratio of activity performed up to a key date as a percentage of total work for the project.
PERCENTAGE OF COMPLETION:
The percentage of completion shows the ratio of the activity performed up to a certain day to the total activity planned for a network activity or WBS element.
EARN VALUE:
The term "earned value" describes the costs incurred to bring a project element to its current degree of completion. To calculate the earned value, the system multiplies the degree of completion by a planning factor, such as the original plan or the budget.
Regards,
ANSAR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
All are fully confirmed or partially confirmed?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Farhan
Remove all weightage assigned to WBSe level.
If weightage is not assigned to activity level then assign them.
Use time pro method in plan and degree of processing in actual. both in activity and wbse level.
Then run cjen, cne1 and cne5 in sequence.
Hopefully you will get accurate figures.
Regards
Dear Farhan
Go to the assign measurement methods as a default value in SPRO. Dont go in the detail screen jst change the measurement method of WBS in Actual from the column directly. Enter 000006 directly. Then you will find the actual values of POC rolling upto the WBSe level.
In progress version keep weight as a standard for calculating POC.
Regards
>
> Dear Farhan
>
> Go to the assign measurement methods as a default value in SPRO. Dont go in the detail screen jst change the measurement method of WBS in Actual from the column directly. Enter 000006 directly. Then you will find the actual values of POC rolling upto the WBSe level.
>
> In progress version keep weight as a standard for calculating POC.
>
>
> Regards
Dear Saqib,
I have done the measurement method already and value is defined - 000006.
In progress version percentage of completion Tab- POC weighting is 7 Cost Plan ( Active Project, Annual values)
Regards,
Farhan