cancel
Showing results for 
Search instead for 
Did you mean: 

why the total float is negative?

Former Member
0 Kudos

Dear all

what do the total float and free float mean respectively?

i see the total float is negative, eg -50

is it wrong? what does it mean?

thanks a lot

Judy

Accepted Solutions (1)

Accepted Solutions (1)

ansar_shaikh2
Contributor
0 Kudos

Critical can be called when Total float equal to or less than zero.

total float = late finish - early finish, late start - early start

Critical path determines the shortest time to complete the projects and it is the longest duration path through a network of tasks.

The cpre of Critical paeth Anlysis is to know how to calculate the ES, LS, EF, EF for an activity in a network diagram using the Forward pass and Backward pass.

Hopw u got it,

Regards,

ANSAR

Answers (5)

Answers (5)

former_member201206
Active Contributor
0 Kudos

Hi Judy,

It is absolutely normal, that the float get negative. It just represents the fact, that typically the inputed finish date can not be gained. The consulting note 151551 should give you some background about network scheduling.

Kind regards,

Zhenbo

ansar_shaikh2
Contributor
0 Kudos

Its Critical path... it will come under critical path method where the total float =< 0

I will later explain you the total float formula.

Regards,

ANSAR

Former Member
0 Kudos

Hello

The definitions of free float and total float are provided in SAP itself. In your case the issue is this particular activity starts 50 days before ts predecessor starts which inturn creates a scheduling conflict. Change the start date of the activity to before its predecessors start date. This scenario is for a basic FS relationship

Depending upon the relationship assigned the reason might vary. Please provide the relationships of that particular activity for the accurate solution.

Regards

Renjith

Former Member
0 Kudos

Dear,

Total float is the time that an activity can be shifted out into the future starting from its earliest dates without affecting the latest dates of its successor or the latest finish date of the network.

Free float is the time that an activity can be shifted out into the future starting from its earliest dates without affecting the earliest dates of its successor or the earliest finish date of the network.

The free float must not be less than zero or greater than the total float.

Regards.

Former Member
0 Kudos

Hi

The scheduling is done with Forward as well as backward process. The difference between the two scheduling process gives the float for the activity. Hence the float comes out in the negative if there is a difference between forward scheduling and backward scheduling

Regards,

Uddhab