WBS Element in Purchase order

Former Member
0 Kudos

hi...

i want to know in project system ,in a project whr i enter WBS element in Purchase Order me21n?

Rekha sharma

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

thanks all of u

Former Member
0 Kudos

Hi

In ME21N, go to item overview and then go to account assignmenet and put "Q"

Now in Item details go to account assignement and there you will find the WBS element to be entered

Uddhab

Former Member
0 Kudos

Dear,

When you put Q for material PO or the P for service PO in account assignment catagory ,then only you can put the WBSE in account assignment tab of PO.

Regards.

Former Member
0 Kudos

Project PO can be generated in following methods.

1.When a Material attached to Activity in the Project, PR can be generated with A/C assignement Q. System wil copy the WBS element to which activity is assigned in the account assignment tab of PR. When PO is created with reference to PR, system wil automatically copy the WBS from the PR in to PO account assignment tab.

2. U can directly create PO with account assignment Q and assign WBS in account assignment tab.