please any one could give transcation flow of PS and PM integration,

thanks in advance,

Mohan M

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Answers (4)

Answers (4)

mohan_madaiah
Active Participant
0 Kudos

closed

Former Member
0 Kudos

Dear,

You can create the Maintenence order as sub network in project system.

Regards.

mohan_madaiah
Active Participant
0 Kudos

hi pushpa

thanks a lot.

very help full answer

regards

mohan

mohan_madaiah
Active Participant
0 Kudos

Hi

thanks a lot venkat....

i am new to PS module..

could give transaction flow in PM and PS modules integration scenario, that serve my purpose ....

regards

Mohan

Former Member
0 Kudos

hi mohan ,

in PS u can create project in CJ20N, define project structure, date planning and in PM you can create MO maintenacne order in iw31 and in additional tab u can assign PM order to network or WBS for budgeting to WBS u can go to cj30 .

regrds

pushpa