cancel
Showing results for 
Search instead for 
Did you mean: 

CJ20N vs CJIC -> different status of distribution rule

Former Member

Hello Experts,

can you please help me with issue in tr. CJID {display project settlement} where I see different status for WBS elements settlement rules.

If the settlement rule is set up via project builder and after processing, the status in CJID is remaining red {no distribution rule assigned}. But if I do the same for another WBS in the same project via CJIC, the status in CJID is green as should be.

Posting and settlement works ok, but only the statuses are weird. Can some advise how to solve this "cosmetic" error. It caused us trouble in reporting.

Thank you!

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

...any ideas???