plan values for Result analysis

Former Member
0 Kudos

Hi Experts,

In result analysis customization i have selected version '1' in valuation methods.

and i am doing my cost planning in version '1' through unit costing. and planned revenues are copied from sales order in version '0'.

when i run result analysis through KKA2 transaction. it is taking planned costs but not planned revenues. for this i want to plan revenues in version '1' under transaction CJR2. but client not accepting for this.

i had tried an option to copy from version '0' to version '1' by CJ9FS . but problem is that it is over writing the planned costs done under unit costing .

please through some light on this scenario

With Regards

Prasanth Nara

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Prasanth,

Use T-code CJ9BS & in selection, tick only " Revenue" , I think this may solve your problem..

Regards,

Ashok Sangal