Milestones with different statuses triggering at the same time

Former Member
0 Kudos

Hi Experts,

I have created a Project with 1 WBS Element and 1 Network.

Under Network i have created 1 activity and within that activity there are 2 Milestones.

1) First Milestone has status 'REL' and a Workflow assigned to it

2) Second Milestone had a status 'CNF' and a diff Workflow assigned to it.

i have used BO MLST_NETW as start conditions in both thw workflows.

I want the 1st milestone to trigger when the Network is release and the second when an activity is confirmed.

My problem is when i change the status to Release both the milestones/workflows are getting triggered.

Please let me know where i am going wrong .

Thank You,

Radhika.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Problem solved by using conditions .