Hi
This is a cost report of Hierarchical based for Actual/Planned Time Series (S_ALR_87100189)
Go to CJ40 and create some planned cost , CJ30 - Budget planned , CJ32 - Release budget for a particular project. Now see the report after consuming the allocated budget.