on 02-13-2009 12:46 AM
Hi Experts,
I just want know the possibility of functional area change at WBS level.
If we assign Functional area at project level, can we change functional area of WBS?
if it is possible then is it possible to assign/change functional area of WBS after releasing the same?
Please update me.
Thanks & Regards
Suresh. J
Hi,
The functional area is assigned to the WBS only. The root WBS can have a different Functional area and the Level 1, 2, 3 etc WBS can have different Functional area. It depends on the Business scenario.
Hope this solve ur query
Regards,
Uddhab
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Functional area is assigned either at project or WBS. This can be changed before any posting is done against this WBS.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Surej,
FA in project is in Basic tab and FA in WBS is in Assignement tab. Both functional area for Project or WBSes could be different. All this functional area could be changed. However, please note if you changed the FA once the data is posted into the WBS, the system will give a warning message not to change the FA. This FA in master data is to ease data entry. The FA will be copied over to FA area field during data entry. In fact, you can change the FA during data entry.
Hope this explains your query.
Thanks.
Regards
Fauzi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.