About CJ40 and CJ41 Tcodes

former_member632729
Contributor
0 Kudos

Hi,

Is their any flow in PS module and what is the use of this tcodes ( cj40and 41). Can any one explain about the Tcodes : CJ40 and CJ41..

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

CJ40 - Planned cost for the respective WBS (as per the estimation of your project)

CJ41 - Display the planned cost of the WBS

Regds,

Uddhab

Former Member
0 Kudos

CJ40 is for Cost Planning at WBS element. This method is used when Network Costing is not used. In CJ40 u can do Overall planning or Annual Planning. Also Cost planning can be done in different version to capture differrnt plans.

CJ41 is to display cost planning done CJ40.

Refer below links.........Topic:Manual Cost Planning in the Work Breakdown

http://help.sap.com/saphelp_erp60_sp/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm

Former Member
0 Kudos

CJ40 allows you to plan costs and activities against the WBS Elements in your project.

CJ41 allows you to display these planned costs.

Before planning you have to make sure that your project/wbs status allows planning. You can plan in a period based manner or according to cost elements. It also allows you to plan using easy cost planning which is a template-based planning system.

Regards,