Query on ATP / MRP

Former Member
0 Kudos

I need to create a new document type (quotation) that will create MRP requirement. But, the quantities should not be considered for ATP. Can u suggest any way.

So, If i have 100 Pieces in the new document - It shold generaed MRP requirement of 100. However, it should not consume 100 from the current stock.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can assign the SAP standard schedule line category L1 or L2 which will transfer the requirements but without Availability check, or create your own schedule line category-

In SPRO > SD > Basic Functions > AC and transfer of requirements > transfer of requirements > define procedure for each schedule line category

Former Member
0 Kudos

When I tried using L2 - it is still including the stock that will be considered for ATP check. The document as such is not going through ATP. But, the document quantity is being taken out of ATP. I don't want ATP quantities for other orders to be impacted.

Answers (1)

Answers (1)

Former Member
0 Kudos

Unanswered.