on 02-12-2009 1:51 PM
Hi,
We are not using the functionality of network of PS in our orgnisation. We would like to put a actual finish date for the WBS element so that further GRN entries can be restricted. Appreciate if someone can guide on this.
Regards,
Anand
By maintaining Actual finish date in WBS wil not restric the GR.
In the Status profile create a User Status (Ex:COMP) and set "Goods receipt for prodn. order" and "Goods receipt for purch. order" as forbidden. Then set this user staus for the WBS once actual date is achieved.