Former Member
0 Kudos

Hi,

I create a PO from the shopping cart portal in SRM, the PO is created in ECC. However, the requested on date in SRM is copied as delivery date in ECC at item level of PO. My requirement is to change the date and add Planned Delivery time(PDT) obtained from material master to the PO create date. Where I need to write the Logic. I am new to SRM and shopping cart?

Regards,

Vishal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Use BADI 'BBP_CREATE_BE_PO_NEW'-->Method

FILL_PO_INTERFACE1

Write your logic into this method.

Regards,

Sachin