Hi experts,
Whenever choosing a material in a project, I get the same error message:
Material XXXXXXX not maintained in plant XXXX
We don't need to store the specific material in the plant, but we want to plan the future purchasing needed for the project.
¿How can we avoid this check?
Thanks in advance.
Kind regards,
Neil
One correction - you do it in MM01 - Create Material Master. Copy the material to same material number, giving new plant.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks,
Does anyone have another idea? The thing is, I need a material for a project, and I know the company is getting it (has it in a plant, or has an out. agreement to purchase it).
Why can't I include it unless I know the plant for which it was defined?
I can't see the logic right now...
Thanks a lot.
Kind regards,
Neil
Hi,
You need to go to MM02 and extend the material master to the plant for which you're running the project. Use the copy function.
Kind regards, Aleksandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check whether the plants parameter are maintained for the plant in inventory management.
Also check whether material valuation and quantity updations are checked in OMS2.
Regards,
Abhee.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.