on 02-12-2009 8:52 AM
Dear all,
please help me on this problem.
i want to close the project.
but the error message is Balance of NWA activity is not zero.
i have used CJ88 to settle the project.
could someone give me some hints?
thanks a lot.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If it is external activity, mark the delivery completed in PO of the activity. and if it is internal activity do final confirmation.
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Settle the Cost to WBS element by entering the network number and activity number in CJ88 with reference to the period and fiscal year.
after that check is there any stock available in the project if so please move that cost to plant stock
then try to close the project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi ,
i think you need transfer your actual costs on acitivity to WBS and then settle your project .. then u can close your project .check tcodes KB21N ,KB65 etc
regrds
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you need to settle the network activity in question
check your settlement rule for the network activity - should be FUL as you might settle for period but there could be some unsettled osts from the last period
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.