To find AR No . against Project

Former Member
0 Kudos

Sirs

to find out which AR is assigned to given Project , is there any transaction / method ?

The said data can be extracted using table IMAK , but whwre can you see the assignment of AR No. to project ?

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Thnax you Sirs

jpfriends079
Active Contributor
0 Kudos

Try Tcode. IMR6 or IMR7.

I hope ur requirment will be fulfilled.

Take care.

Thanks & Regards

J Prakash

Former Member
0 Kudos

hi

you can get the details from this structure. RAIA1

Former Member
0 Kudos

Hi,

If Project structure is created automatically through AR in your case,go to t code IMA11.

1. Double Click the Appropriation Request (listed on the left of the screen). This will display the AR to

be processed

2. Press Change ( Pencil icon).

3.Select the Measures/Assets tab.

4.Click the WBS Element button

5.The resulting window will inherit the Project and WBS Element number from the AR number.

Regards

Tushar

Former Member
0 Kudos

Hi,

In the project we define the settlement rule where the Cost centre is assigned. In the cost centre the GL account for the particular AR (account receivables) is assigned which reflects the actual posting of the accounting document.

Hope your question is answered as per your requirement. Please feel free to contact if any more information is required.

Thanks

Uddhab Paul