Hi Gurus
My AVC is active in PS, but in F-47 and F-48 transactions, budget is not committed, means controlling document is created with Advances cost element assigned in SPRO . it is working fine in other transactions but i didn't find any solution for F-47 and F-48 . Please help
Hi,
Please check CJ30 and then CJ32 for budget allocation and budget release respectively.
Regards,
Uddhab
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
please check your tolerance limit settings. whether it checks for all the activities.
it should be "++".
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check tolarance limit set up. check it is set for transaction group financial accounting document.
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.