Hi Experts,

Can anybody please explain planning strategy 11 in short.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Friend,

Make to Stock with Gross Requirement planning:During net requirement planning it wont consider the stock.Mainly used for the mass production companies where they go on producing and doesnt want to have stock planning.

STRATEGY 11-In the case of gross requirements planning, no warehouse stock is taken into account. Only receipt elements are included in the net requirements calculation.

Edited by: SUNIL on Feb 11, 2009 5:31 PM

former_member550050
Active Contributor
0 Kudos

Dear Raja

Check this thread

Forum post in SCM - PP: PIR Reduction in strategy-11

Regards

Raja

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear Raja

Go through this help link

[Gross Requirements Planning (11)|http://help.sap.com/saphelp_47x200/helpdata/en/a2/4e799d927d11d1800f00c04fadcb73/frameset.htm]

thanks