on 02-11-2009 6:53 AM
Hi,
I have an issue with GI date increasing by 7 days when we do picking by vl06p.
Delivery copies with the exact dates of the sale order but once the picking happens the GI date adds up to next 7 days. we have route schedule active, but the Actual PGI was before the Route Schedule date,even then 7 days are added to GI date
please help
dear Varada,
check in the material master whether the planned del time and GR processing time is mentioned in MRP2 view.
May be because of that you are having 7 days difference.
Regards,
Sudhir