on 02-10-2009 10:24 PM
Hello expert...
I run in to unique problem, Here is my situation... I have created WBS and assigned component with procurement type E - In-house production (finished material with planning strategy 85 - Assembly processing with network/project). MRP is creating planned order for particular project requirement. When converting to Planned Order to Production Order, system is not automatically copping WBS - Project as account assignment category on production order. What settings am I missing to copy automatically WBS to Production Order while converting planned order to PO?
Thanks
hi
please check this setting is active in your Asset accounting.
Financial Accounting (New) -->Asset Accounting -->Integration with the General Ledger -->Additional Account Assignment Objects -->Activate Account Assignment Objects
Financial Accounting (New) -->Asset Accounting -->Integration with the General Ledger -->Additional Account Assignment Objects -->Specify Account Assignment Types for Account Assignment Objects
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have made some master data changes and created new master data, that solved the problem.
Now the problem is when I conver planned order to production order, system is setting-up finished material as non-valuaded by default. Also order settlement does not create any data to settlement. On project side also cost is not flowing.
Thanks in advance for help.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.