rescheduling - V_V2

hello!

i am evaluating rescheduling functionality in SAP (V_V2). rescheduling works, but it does not consider dependent requirements from planned orders.

i have following situation

- stock 7 pc

- 1.3. cusord -5pc -> confirmed

- 5.3. depreq -2pc

- 10.3. cusord -2pc -> confirmed

i would expect that the second customer order is not confirmed, as i do have an earler dependent requirement. in customizing of checking rule 'A' dependent requirements are included.

thanks for help!