Hello All,

I have a requirement as below:

- Normally, when we do a shipment and in that if the shipment is relevant for shipment cost calculation then system would pick the pricing date = shipment end date in standard SAP.

But, my requirement is that the pricing date should be = shipment start date.

So, is this possible via standard SAP customization thing or do I need to look for an User Exit which will overwrite this pricing date in shipment?

Appreciate your valuable response at earliest.

Regards,

Hrishi

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

the Pricing date for the shipment document is determined based on you shipment cost item category. Transportation- Shipment Cost - Shipment COst Document - Shipment Cost Types and Item categories - Define item categories.

You can also define new roles in Basic Functions - Date Rules.

Good Luck

Former Member
0 Kudos

Hi,

Thanks for your response.

I will test the same by tomorrow and let you know about the results if they are as per requirement or not.

Regards,

Hrishi

Answers (2)

Answers (2)

Former Member
0 Kudos

Closing the thread

Former Member
0 Kudos

Await your kind response.

Regards,

Hrishi