Document number of Planned cost booked on Project system

Former Member
0 Kudos

Hi All,

I have a requirement wherein i need to find out the document number of the cost booked in Project and WBSE. Like for eg in Report S_ALR_87013532, there is planned cost.

also in the same report S_ALR_87013532, we have OVERALL VALUES and TOTAL OF YEARS. What is the difference between the two ?

Thanks in Advance

Regards,

Ajay

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

you can check in the table RPSCO.

Former Member
0 Kudos

hi

overall value is the Total Cost ir respective of years.

Annual value is for that annual year how much is the cost.

Former Member
0 Kudos

my doubt is regarding Overall values and Total of years. Year wise its OK.

Former Member
0 Kudos

RPSCO table does not have document numbers

Former Member
0 Kudos

hi

check in this structure KAEP_COAC

Former Member
0 Kudos

Overall is derived from the Overall values planned for the project (at the overall level) - look at config of your planning profile - transaction OPSB.

Total of Annual is the sum of the all annual values planned for the project.

To get the document number, you will need to go to the line items. To go there, select the WBS element or whichever level you want to drill down to and then goto menu Goto -> Line items. You will be given a list of line items available (actual, plan, etc...). Once you get in there, you should be able to select the "Document number" field from the available fields or click on the "Document" item to view the posting document.