Budget Control - trouble

Former Member
0 Kudos

Friends,

Scenario is like this:

Client is upgrading from 4.6C to ECC 6.0. They are creating PR through Network and therefore the GR happens with Network as Account assignment. But the budget control is done with respect to WBS element. They have activated Budget Availability Control in ECC 6.0 using a package. Now they want to control the PO with respect to WBS element. How can they do that?

Please help.

Thanks,

A

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

answered

Former Member
0 Kudos

Hello..

please suggest..

basically, GR has the account assignment of network, but budget is done on WBS elements. How can I change account assignment in this GR to the concerned WBS element.

Ideas appreciated..

Thanks,

A

Former Member
0 Kudos

Network is assigned to WBS element. cost from network flows to assigned WBS element and network cost is controlled through WBSE.

Sudhir

Former Member
0 Kudos

It requires MM config. SPRO> Material Mangment> Purchasing >account assigment> Maintain account assigment catgory. Then for account assigment catagory for project, check the Acc. assign changable.

Regards,

Sudhir

Former Member
0 Kudos

Check tolerance limit setting. tolerance limit for buisness transaction group PO is required. If it is maintained for all transaction group, it is ok. Run CJBN for project to reconstruct availability control.

Sudhir

Former Member
0 Kudos

Problem is about account assignment from Network to WBS element... tolerance limit is not in question at all...