I´m using SNP, with standard situation, just a safety stock form Raw material and once Stock Level falls down of SS, system place a PurchReq, I have a problem due to during 3 weeks per year, plant is not able to receive, purchreq, so I need to place them forward till the first date available,
I have used a handling resource but is only detected with Optimizer, the problem is that I am working with a fix lot 155000 m3 but optimizer does not respect this lot
Could you please help me to sort out this issue?
Thanks in advance
Hi Rafael,
You can create a time stream id without these 3 weeks and assign it in the transportation lane. This ensures that the system creates purchase reqs. at the receiving location (plant) only on those days in time stream. If a day falls with in the 3 weeks, since the day is not in the time stream, it takes the next day in the calendar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.