cancel
Showing results for 
Search instead for 
Did you mean: 

Work center valuation

Former Member
0 Kudos

Hello,

I'm working in an organization where we use a lot of cost center. Meanwhile, i dont want to create as many work center as existing cost center (huge amount), even if i want to make a different valuation for the planned costs of my different cost centers.

Is there any possibility to calculate the costing of a network activity with a different way than the cost center-activity type combination stored at work center level?

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

I think the answer is No for internal activity type. But if you want to only plan the cost through activities then try the option of using cost actvities where in you can key in the amount to be planned, the restriction in this case would be actuals has to be posted separetly..means activity confirmation won't give you the actuals...

Regards

Answers (0)