on 03-16-2006 11:00 PM
I am studying the XI tutorial "How to create XI Content with the Integration Builder". Every step in XI is described in detail, but no details about what to do in the R/3 System.
Section 6.1 is saying that I must customize the SAP backend so that the backend system can send an IDOC to my external system. As I have little experience with SAP I do no know which transaction to use and in which order.
Please give some help.
The IDOC is MATMAS01. I have completed the definitions of my external system in the SLD. I already made a port using WE21. To do is defining the outbound scenario MATMAS01 from r/3 to External.
The following configuration required in SAP to create an IDOC and configure to XI system.
1. Create/identify the TWO logical systems one for R/3 and other for XI.
2. Define distribution model with BD64
3. Define RFC destination in R/3 for XI with SM59 tcode.
4. Create port using WE21.
5. Create partner profiles using WE20.
Testing:
6. Use BD10 to create a Material master idoc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
78 | |
10 | |
9 | |
7 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.