cancel
Showing results for 
Search instead for 
Did you mean: 

Lock Table Overflow because of ALM_SENDER_ESCALATION job

HJ1
Participant
0 Kudos

Hi,

we are getting Lock Table overflow in our system becasue of this job is running.

ALM_SENDER_ESCALATION

Details:

I have done the CCMS alert monitoring Configuration in SOLMAN4.0

we have configured ALM.

we have made client 000 as CEN and 100 as ALM

so all the alerts are getting transferred from CEN to ALM by one

autoreaction method and this is running by one job

ALM_SENDER_ESCALATION...

and because of this job we are getting lot of error like lock table

overflow....

we are using the System monitoring functionality in Solution

Manageror just using CCMS till now.

Please Help

Regards,

Harish

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi harish ,

Please try the Note: 746138

Regards,

Kiran M