Dear PS Experts,
I have created three network activities,
i attached 1st milestone to the 1st activity using the function " release to stop indicator" and the system status which i chosen was 'REL'
Then second milestone to the third activity and marked it as stop indicator.
But when i m releasing the 1st activity, other activities are not getting released automatically.
Can anybody tell me...wats the mistake ???
Thanks in adv.
Regards
Ashis
Ashis,
In order to make this work you should set the milestone Funtion "release up to stop indicator" in the first activity.
In the third activity, you should create another milestone and set the flag "stop indicator".
Then you should link activities 1 2 and 3 with relationships. If the activities are not linked, the function to release up to stop indicator will not be triggered.
Can you please check if this is the case?
Thanks
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.